2026 guide · execution
Apartment finishing stages, in order and on schedule
Most finishing problems come from the wrong order: tiles before the flood test, paint before the gypsum, doors ordered too late. Here's the right sequence, what must be finished before each stage, and what to inspect before moving on.
Finishing a 150 m² flat from red brick takes about 12–16 weeks (81 working days) with one crew per trade; 9–13 weeks if it's handed over plastered and 7–10 weeks if semi-finished. The order: electrical and plumbing rough-in → plaster → gypsum → tiling and marble → paint → aluminium and doors → electrical and plumbing finish → handover.
Schedule from Tashteeby's engine · 6 working days a weekThe schedule for a 150 m² flat
Many stages overlap: paint starts with putty and sealer during tiling, and aluminium and doors are made in the workshop early on and fitted after the tiles.
The stages in order — and what to inspect at each
Duration by unit condition
| Condition | Duration | Working days | Cost |
|---|---|---|---|
| Red brick | 12–16 weeks | 81 | 774,144 |
| Plastered | 9–13 weeks | 64 | 692,481 |
| Semi-finished | 7–10 weeks | 52 | 536,933 |
| Old finish (renovation) | 10–14 weeks | 73 | 734,104 |
Frequently asked questions
What's the order of finishing stages?
How long does a 150 m² flat take?
Gypsum before or after tiling?
Paint before or after the doors?
How can I shorten the schedule?
Price your own project
The same engine behind these numbers, with your area, rooms and finish level — the total is free, no sign-up.